Services
Sustainable Energy Solutions
Mechanical & Electrical Engineering
Sector
Healthcare
Local Councils & Government
Value
c£86,000
Programme
6 weeks
Client
Crawley Borough Council
Location
West Sussex
Contractor
Mitie
A local council owned sheltered housing property in Maidenbower, West Sussex.
The requirement was to work in partnership with Crawley Borough Council and their housing repairs contractor, Mitie, to install a sustainable energy solution to provide space heating and hot water to the tenants of Schaffer House.
Baystar installed a 70kW water source heat pump to replace the two existing boilers, alongside a brand new backup boiler, a new radiator programme and a complete plant room upgrade.
The council will see a combined annual income and savings of up to £12,700 and a carbon reduction of c50%.
A project of this size will earn c£8,000 per annum in Renewable Heat Incentive payments for 20 years, and the fuel cost saving will be approximately 10%.